Underground | LJB Inc. https://www.ljbinc.com Civil and Structural Engineering | Environmental and Safety Services Thu, 22 Jan 2026 14:39:05 +0000 en-US hourly 1 https://wordpress.org/?v=6.9 https://www.ljbinc.com/wp-content/uploads/2023/12/cropped-LJB-logo-favicon-32x32.png Underground | LJB Inc. https://www.ljbinc.com 32 32 Olentangy Augmentation Relief Sewer (OARS) Construction Management https://www.ljbinc.com/project/olentangy-augmentation-relief-sewer-oars-construction-management/?utm_source=rss&utm_medium=rss&utm_campaign=olentangy-augmentation-relief-sewer-oars-construction-management Fri, 21 Nov 2025 16:34:42 +0000 https://www.ljbinc.com/?post_type=project&p=13187

Role: Construction Management, Technical Support Client: City of Columbus Construction Cost: $375 Million Technology: EPBM/Slurry TBM Geology:  Karst limestone Diameter: 20 ft (6 m) Length: 23,000 ft (7010 m) Depth: 200 ft (50 m) Project Elements: Combined Sewer Overflow (CSO) Tunnel in urban environment Deep shafts (access and drop shafts) Slurry wall construction Drill and blast shafts, adits, […]

The post Olentangy Augmentation Relief Sewer (OARS) Construction Management first appeared on LJB Inc..]]>
Westside Purple Line Extension, Phase 3: Rail Transit Line https://www.ljbinc.com/project/westside-purple-line-extension-phase-3-rail-transit-line/?utm_source=rss&utm_medium=rss&utm_campaign=westside-purple-line-extension-phase-3-rail-transit-line Fri, 21 Nov 2025 16:19:27 +0000 https://www.ljbinc.com/?post_type=project&p=13183

Role: Tunnel Design Lead; Design Build for Contractor Client: STV Inc. Construction Cost: $1.27 Billion Technology: EPBM Geology:  Soft Ground Dimensions: 20.3 ft ID (6.1 m) Length: 2.6 mi (4.2 km) Depth: 50-70 ft (15-21 m) Project Elements: Twin-bore tunnel in dense urban environment Santa Monica fault – 700 ft wide at 63⁰ Undercrossing critical highway and water […]

The post Westside Purple Line Extension, Phase 3: Rail Transit Line first appeared on LJB Inc..]]>
Alaskan Way Viaduct Replacement Program https://www.ljbinc.com/project/alaskan-way-viaduct-replacement-program/?utm_source=rss&utm_medium=rss&utm_campaign=alaskan-way-viaduct-replacement-program Fri, 21 Nov 2025 16:16:34 +0000 https://www.ljbinc.com/?post_type=project&p=13181

Role: Cost and Risk Verification Check and Expert Review Panel Member Client: Washington State DOT Construction Cost: $3.1 Billion\Technology: EPBM and Cut and Cover Geology:  Soft Ground Dimensions: 58 ft (17.6 m) Length: 9600 ft (2.9 km) Depth: 20-50 ft (6-15 m) Project Elements: Single-tube double-deck tunnel Two lane highways on each level with 50 mph design speed […]

The post Alaskan Way Viaduct Replacement Program first appeared on LJB Inc..]]>
Underground Services https://www.ljbinc.com/services/underground-services/?utm_source=rss&utm_medium=rss&utm_campaign=underground-services Tue, 18 Nov 2025 21:00:09 +0000 https://www.ljbinc.com/?page_id=12995 Underground Services Contact LJB Underground Services Engineered Solutions for Complex Underground Structures LJB Underground Services specializes in underground infrastructure, bringing unmatched tunneling, geotechnical and structural expertise to support projects from early planning and design to construction oversight. With 15+ years of experience on more than 100 tunneling projects worldwide, we have worked on some of the most […]

The post Underground Services first appeared on LJB Inc..]]>
Montreal Airport Station, Transit Terminal for REM https://www.ljbinc.com/project/montreal-airport-station-transit-terminal-for-rem/?utm_source=rss&utm_medium=rss&utm_campaign=montreal-airport-station-transit-terminal-for-rem Thu, 13 Nov 2025 18:48:33 +0000 https://www.ljbinc.com/?post_type=project&p=13128

Role: Tunnel, Shaft and Station cavern Design – Precast Concrete Liners, Connections and Complex Fault Crossings Client: Aeroports de Montreal Construction Cost: $600 Million Technology: Drill and Blast Geology: Rock Length: 815 ft (250 m) Diameter: 31 ft (9.6 m) with 79 ft (24 m) span cavern Depth: 86-142 ft (26-43 m) Project Elements: Design of cavern under terminal building Access […]

The post Montreal Airport Station, Transit Terminal for REM first appeared on LJB Inc..]]>
Rebecca Trunk Wastewater Main https://www.ljbinc.com/project/rebecca-trunk-wastewater-main/?utm_source=rss&utm_medium=rss&utm_campaign=rebecca-trunk-wastewater-main Thu, 13 Nov 2025 18:44:44 +0000 https://www.ljbinc.com/?post_type=project&p=13125

Role: Microtunnel Designer & Construction Inspection/Administration Client: Cole Engineering Construction Cost: $43 Million Technology: Drill and Blast Geology: Rock Diameter: 1,200mm (48 in) & 1,350mm (54 in) Length: 12,476 m & 1,575 m Depth: 14 m (46 ft) Project Elements: Fourteen (14) microtunneling drives Twelve (12) composite curved drives Long microtunneling drives from 180m to 626m Concrete caisson shafts Shallow […]

The post Rebecca Trunk Wastewater Main first appeared on LJB Inc..]]>
Atlanta Airport Plane Train Turnback Tunnel https://www.ljbinc.com/project/atlanta-airport-plane-train-turnback-tunnel/?utm_source=rss&utm_medium=rss&utm_campaign=atlanta-airport-plane-train-turnback-tunnel Thu, 13 Nov 2025 18:38:51 +0000 https://www.ljbinc.com/?post_type=project&p=13123

Role: Owner’s Engineer for tunnel and Access Shaft; Progressive Design Build Client: Ricondo Construction Cost: $140 Million Technology: CSEM, Drill and Blast Geology:  Soil/Rock Dimensions: 22 ft (6.7 m); Tunnel bifurcation up to 48 ft (14.5 m) span Length: 1780 ft (237 m) Depth: 36-55 ft (11-17 m) Project Elements: (x1) Access Shaft – 36 ft ID x […]

The post Atlanta Airport Plane Train Turnback Tunnel first appeared on LJB Inc..]]>
Crenshaw/LAX Transit Corridor https://www.ljbinc.com/project/crenshaw-lax/?utm_source=rss&utm_medium=rss&utm_campaign=crenshaw-lax Thu, 13 Nov 2025 17:09:19 +0000 https://www.ljbinc.com/?post_type=project&p=13041

Role: SOE Design of Stations; Design Build for Contractor Client: Walsh-Shea Constructors Construction Cost: $1.27 Billion Technology: Cut and Cover Geology:  Soft Ground; Young and Old Alluvium Dimensions: 3 stations, each 806 x 110 ft (245 x 33 m) – 70 ft (21 m) diameter Length: 13,728 ft (4 km) Depth: 67-71 ft (20-21 m) Project Elements: Basis of […]